Richmond Coliseum demolition expected to wrap up by December 2027
Design work on the teardown finishes next spring, and the city will ask council in December to accept $15 million in state money to pay for it.
The Richmond Coliseum should be gone by the end of 2027. Mayor Danny Avula said Tuesday that pre-demolition planning for the vacant downtown arena is underway and that demolition and site work are expected to be finished by December 2027.
Engineering firm Timmons is handling the planning and design work ahead of the teardown, which the city expects to wrap up in the second quarter of 2027. In December, the Avula administration plans to introduce legislation asking Richmond City Council to formally accept $15 million from the Commonwealth of Virginia and create a dedicated Richmond Coliseum Demolition Fund.
“The City of Richmond is making meaningful progress towards the redevelopment of the Coliseum site and broader City Center area, including the long-awaited demolition of the Richmond Coliseum,” said Danny Avula, mayor of Richmond.
Where the money comes from
State lawmakers set aside the $15 million in the two-year budget they approved in June, after Sen. Lamont Bagby pushed for the funding. The dedicated fund is meant to keep that money tied to the demolition and site work. In his statement, Avula said the goal is to make sure the state’s investment in downtown redevelopment “is used in a timely and accountable manner.”
The Greater Richmond Convention Center Authority, which operates the convention center next door, also plans to commit money to the project, according to the mayor’s office. The statement did not say how much. The city’s Economic Development Authority owns the Coliseum property.
“These are important steps to finally move this project forward, and I’m truly grateful for the partnership with the Commonwealth, the City’s Economic Development Authority, and GRCCA and Timmons for helping to make this possible,” Avula said.
What comes next for the site
The Coliseum opened in 1971 and has sat empty since it closed in 2019. An earlier plan to replace it, the $1.5 billion Navy Hill project, fell apart in 2020 when City Council voted it down.
Clearing the arena is the first step in the city’s revived City Center redevelopment. City officials have discussed a hotel of roughly 500 rooms to support the convention center, but Tuesday’s statement did not address what will replace the Coliseum. Avula said the city will keep working in the coming months to “unlock the potential of this part of our downtown for the residents of Richmond and the greater Richmond region.”
City Council is expected to take up the funding legislation in December. More information is available at rva.gov.