We are continuing to get questions re: the stalled work on the Forest Hill Avenue project and an update on the Jahnke Road project. Here is a timeline update on both projects and a link to overall project plans.

The FH Avenue project unexpectedly ran into some utility issues about 6-8 weeks ago but according to the timeline we received, they expect resolution by the end of August.

Forest Hill:
• Underground Utility work- July- August 2019
• Roadway Work to commence – September 2019
• Complete Construction – March 31, 2021
http://www.richmondgov.com/…/ForestHillImprovementProject.a…

Jahnke Road:
• Right of Way Acquisition complete (84 parcels)
• Utility Coordination/Relocation underway completion January 2020
• Re-Advertisement for Construction – Winter 2020
• Construction to begin Spring 2020
• Construction: 2 years to complete roadway construction, finishing Winter 2022
http://www.richmondgov.com/…/JahnkeRoadImprovementProject.a…

Will you help support independent, local journalism?

We need your help. RVAHub is a small, independent publication, and we depend on our readers to help us provide a vital community service. If you enjoy our content, would you consider a donation as small as $5? We would be immensely grateful! Interested in advertising your business, organization, or event? Get the details here.

Richard Hayes is the co-founder of RVAHub. When he isn't rounding up neighborhood news, he's likely watching soccer or chasing down the latest and greatest board game.