Overnight detours on Broad, 14th, and Main Streets

Overnight detours on Broad, 14th, and Main Streets

Detours will adjust each night as work progresses through the intersections. Drivers are encouraged to pay close attention to Maintenance of Traffic (MOT) signage indicating differing lane closures overnight in locations where the traffic signal work is occurring.

From Ride GRTC:

Traffic signal work continues to progress for the Pulse project, advancing through intersections on Broad, 14th and Main Streets. This work is permitted during both day and night. As this work moves across streets and intersections, LANE Construction may implement some temporary overnight detours.

Detours will adjust each night as work progresses through the intersections. Drivers are encouraged to pay close attention to Maintenance of Traffic (MOT) signage indicating differing lane closures overnight in locations where the traffic signal work is occurring. Anticipated schedules are detailed below. For assistance, please call the Pulse Construction Hotline 804-980-0084.

WHO:              DB Contractor, LANE Construction

WHAT:             Night traffic signal work (trenching – cutting into the roadway and sidewalk) at various intersections along the Pulse route. Lane closures, including overnight closures, are being coordinated to provide the least amount of disruption to traffic.

WHEN:            Beginning 6 PM Sunday, June 18, 2017 (subsequent nights permitted between 6 PM and 6 AM, Sundays through Thursdays; however, progress may require some work extend to daytime hours).

WHERE:           The following intersections, estimated as follows. Work is weather- and progress-dependent.

Sunday night, June 18:
College St. closed at College St./Old 14th and Broad St. (EB & WB Broad St. remain open)
EB Main St. closed at14th St. (WB Main St. remains open)
Monday night, June 19:
WB Main St. closed at 14th St. (EB Main St. remains open)
EB Main St. closed at 17th St. (WB Main St. remains open)
Tuesday night, June 20:
SB 14th St. closed at 14th and Main St. (NB 14th St. remains open)
WB Main St. closed at 17th St. (EB Main St. remains open)
Wednesday night, June 21: 
NB 14th St. closed at Main St. (SB 14th St. remains open)
NB 17th St. closed at Main St.
Thursday night, June 22:
NB 17th St. closed at Main St.
EB Main St. closed at 18th St.

BRIEF: Depending on proximity to the work zone, those in the area could hear portions of the construction work. All work is being done within permitting guidelines, including allowed noise levels. This traffic signal work includes cutting into the roadway and sidewalk at intersections. This work is for traffic signal modifications and the foundation for a Transit Signal Priority (TSP) system to expedite the buses moving through traffic signal-controlled intersections. TSP will improve schedule adherence and transit travel time efficiency while minimizing impacts on normal traffic flow.

It is important to note that field conditions can change rapidly and LANE’s goal is to work safely and swiftly to minimize impacts to the areas where they work. The schedule is progress- and weather-dependent. Pedestrian pathway detours and street lane closure signs will be posted accordingly. Please follow construction signage and be aware of construction workers and vehicles within the work zone(s). Pedestrians are advised to follow work zone signage in the sidewalk area. Travelers may notice temporary barriers while this closure is in effect.

BACKGROUND: During construction, the public will continue to have access to businesses, organizations and services located along the Project route.

A construction hotline is active at 804-980-0084, providing updates on construction and expected impacts. For updates online, please visit the Pulse Construction Updates page: http://www.ridegrtc.com/brt/construction-info and explore more at PulseRVA.com. As work progresses, frequent updates will be provided.

LANE Construction will proactively minimize disruption to businesses and residents during construction. Any activity that would impact parking, loading zones, access, utilities and other business-related functions must receive approval from VDOT who will ensure that continuous access will be provided to all businesses at all times. All Project team members are committed to providing prompt information to ensure a smooth construction phase for businesses, residents and patrons of the region as part of the overall success of the Project. For the City of Richmond Pulse Business Support Initiative, please visit PulseRVA.com.

As always, work is weather and progress-dependent.

GRTC Pulse is a modern, high quality, high capacity rapid transit system that will serve a 7.6-mile route along Broad Street and Main Street, from Rocketts Landing in the City of Richmond to Willow Lawn in Henrico County. The Pulse will link the public to many exciting destinations, businesses, services and restaurants.