Bridge replacement and Dock Street project to complicate travel in the coming year

There are two projects going on. The bridge replacement will be done by August and the new round about at E. Main and newly relocated Dock will not be completed in the the fall.

Published

on

x

Commuters and residents have detours and delays as they enter the city from Route 5. The reason is several construction projects in the area. An old railroad bridge needs to be replaced, Dock Street is getting moved and a round about is being put in at E. Main & Dock Street.

Photo: VDOT

Varina Community Connections (hat tip to CHPN for posting this first) has this nice summary:

Happy New Year!
If you use Rt. 5 for your commute into the city you will have a detour at Rocketts Landing starting January 3rd. After a few emails and phone calls here is what I received from VDOT and the City of Richmond

From VDOT

There are actually 2 separate projects in the same general vicinity. The first is the Rt 5 bridge replacement project being administered by VDOT. This project will replace the structure over Norfolk Southern Railroad. This is the project that will close RT 5 on January 3rd. A short detour will be in place during construction which is expected to last until July 21, 2017.

From Richmond City

East River Front Transportation Improvement Project as follows:

  1. Phase I East Main street improvement from Nicholson street to the newly constructed round about at the intersection of E. Main street and new Relocated Dock street, construction will start around mid February and scheduled for completion by September 1st
  2. Continue roundabout construction plus retaining wall and new relocated Dock street construction will continue further and scheduled completion date is January 2017.

City of Richmond is using same detour plans as VDOT RTE 5 Bridge Project which is attached to this e mail. Traffic will be detoured to Williamsburg avenue then to Nicholson street to Rockets Landing and E. Main street will be closed to traffic for phase I of the Project. Once phase I is completed E. Main street will be opened to traffic and Dock street as well as water street will be closed.

A summary from the City on the work that is to take place on E. Main and Dock Street. The summary hasn’t been updated to reflect the decision to install a round about.

  • Dock Street will be relocated from Pear Street to Peebles Street with a roundabout at the Main Street intersection.
  • East Main Street will be widened to include parking, sidewalk, bike lanes, landscaping, and BRT bus pullouts.
  • The intersection at Main Street and Nicholson Street will be evaluated to determine if a signal or roundabout is needed.
  • Sidewalk and landscaping will be added along Nicholson Street and extend to the railroad bridge.
  • Closure of Water Street between Nicholson Street to Ash Street.

Will you help support independent, local journalism?

We need your help. RVAHub is a small, independent publication, and we depend on our readers to help us provide a vital community service. If you enjoy our content, would you consider a donation as small as $5? We would be immensely grateful! Interested in advertising your business, organization, or event? Get the details here.

Richard Hayes is the co-founder of RVAHub. When he isn't rounding up neighborhood news, he's likely watching soccer or chasing down the latest and greatest board game.