City of Richmond announces plan for repairs to Tredegar Pipeline Trail Pipe following sewage spill
The City of Richmond continues to work with the Department of Environmental Quality (DEQ) regarding two isolated events that occurred during July 2024 at the Tredegar Pipeline Trail.
The City of Richmond continues to work with the Department of Environmental Quality (DEQ) regarding two isolated events that occurred during July 2024 at the Tredegar Pipeline Trail. These are two separate incidents and not a continual leak. Initial investigation showed that the first leak on July 2 was related to a wet weather event and was exacerbated by a stormwater connection from an adjacent commercial property. The City reported this to DEQ within 24 hours as required. The City of Richmond Department of Public Utilities confirmed there were no leaks on July 3. There were also no citizen reports of the pipe leaking for the two weeks between the two incidents. The July 2 incident has been closed by DEQ.
The second incident was reported to the City on July 15, and the city immediately responded. The repairs are ongoing and the updates are outlined below.
The Department of Environmental Quality and Virginia Department of Health (VDH) continue to monitor the impacts to the river. Sampling will continue to determine when the Recreational Water Advisory for the James River from Manchester Bridge to Osborne Landing will be lifted by VDH, when VDH determines bacteria levels are acceptable for recreational contact. The City is meeting regularly with DEQ and VDH to continue collaborative conversations regarding repairs.
The City of Richmond continues to address the 42″ failed pipe at the Tredegar Pipeline, which is a combined sewer system pipe. Long term and short-term actions include the following:
1. Â Installation of two large 42″ inflatable plugs
* Â Â The plugs are designed to close off segments of the sewer line from any flow while repairs are taking place.
* Â Â Installation of the large inflatable plugs started July 18, 2024 and one plug was successfully installed. Installation of the second plug is in process.1. Â A temporary patch to the impacted area of the pipe (i.e. under the belly of)
* Â Â Consisting of epoxy and steel plates which are designed to seal all leakage points.
* Â Â This work began Monday, July 22, 2024 and has been challenging as crews have had to consider workarounds based on the location and complexity of the impacted area.
1. Â Isolation of the damaged line segment to prevent any additional flow into the pipe* Â Â A welder was onsite July 18, 2024 to assess the feasibility of a more permanent option. The assessment identified the solution to install metal flanges, which will be welded in place to completely isolate both ends of the pipe. This work is expected to begin the first week of August 2024.
The longer-term and more permanent solution requires an in-depth engineering design and coordination. This 42″ pipe is elevated above the river, where access and the ability to mobilize repair crews are challenges.
The City of Richmond is an old city with aged infrastructure. The Department of Public Utilities is responsible for a territory which includes 5,000 miles of water, sewer and gas pipes as well as 200,000+ other assets (i.e. fire hydrants, meters, valves). Condition assessments help to inform repair, rehabilitation and replacement schedules.